A 900MW data centre campus requiring up to US$16bn in private investment has been proposed for the town of Sutton in Massachusetts, US.
Backed by The Kraft Group and Unified Global Packaging Group, the tentative development envisions constructing 10 distinct facilities on a site located off Boston Road. The first phase of the expansive project aims to deliver two 90MW buildings, covering approximately 23,000 square metres each, by 2029.
Subsequent development phases would add two additional facilities annually until the site reaches its full 10-building capacity in 2033. To manage the immense 900MW energy requirement, the developers are currently negotiating power supply agreements with regional grid operator ISO New England, while evaluating the integration of treated wastewater for cooling systems.
This high-capacity infrastructure project reflects the rapidly escalating demand for dedicated power resources required to support advanced artificial intelligence workloads.
Track more details on Sutton Data Centre Campus project directly on EICDataStream.