The Ministry of Energy of Uzbekistan has announced that it has now signed project agreements with Abu Dhabi Future Energy Company PJSC (Masdar) for the two 220MW photovoltaic solar plants in the Jizzakh and Samarkand regions.
In May 2021, Masdar was awarded the two projects after an open tender overseen by the International Finance Corporation (IFC). 
According to the newly signed project agreements, Masdar will produce power for the National Electric Grid of Uzbekistan at record low tariffs of 1.791 US cents/kWh for the Samarkand site and at 1.823 US cents/kWh for the Jizzakh site, for a 25-year period.
Masdar is expected to invest up to US$300m in these projects with a financial close scheduled for December 2021 and construction anticipated to start in Q1 2022.